33kV Cable Installation – Rownhams

FlowNet was appointed by one of its clients to install six 33kV power cables across approximately 1,500 metres in Rownhams.

The works were delivered against a tightly coordinated programme, with the client’s jointing teams already scheduled to follow immediately behind the installation. Maintaining progress was therefore critical to the wider project sequence.

Despite working through temperatures reaching 38°C, the FlowNet team kept the installation on programme and completed the cable pull safely within the required timeframe.

PROJECT OUTCOME
Six 33kV cables installed across approximately 1,500 metres, safely delivered to programme and ready for the client’s jointing teams.

Another challenging cable installation safely delivered by the FlowNet team.

Previous